Pictures are of Halliburton’s trucks during the frac job
Below is a brief on my accomplishments during the third week of my internship.
June 4, 2010 – Day 9: Riding with a lease operator
I began reviewing the documents sent to me by Weatherford about the CVR. There is a lot of terminology, but from what I gather, it is the combination of plunger lift, foaming, and surface area reduction in order to reduce the critical velocity of the well.
June 5, 2010 – Day 10: Siberia Ridge Frac Job
Today I observed the hydraulic fracturing of the Siberia Ridge well in the Wamsutter (Almond) formation.
Stage 1 – Lower Almond – 30 vis Hybor G
Stage 2 – Almond Bar – 30 vis Hybor G w/ 30Q N2
It was done in two stages each broken up into many subsections. First we pumped perforating fluid (sand suspended in water, creating a mucus-like substance) in 13 distinct stages increasing . We flushed the well using water to clean it and plugged the well.
The plug is attached to several fracturing charges and lowered over 10k ft into the well using an e-line wire line truck. During the plugging stage, the plug malfunctioned due to a lack of oil in the hydraulics and forced us to bring the entire device back to the surface to inspect and perform maintenance on it.
The plug was placed above the initial perforations, and new perforations were made above the original ones at regular intervals. The hydraulic fracturing process was repeated on these new fractures, this time also incorporating N2 into the mix to aid the fracturing process.
After the fracturing process, a different company manages the flow back, which relieves the pressure which built up within the well during fracturing. First, N2 comes up with negligible amounts of water. When gas starts flowing from the well, it will be flared for a while. Once the well is cleaned out, it will be diverted to sales until the tubing can be installed.
The field engineers working for Halliburton served as project supervisors and monitored the entire procedure. Using several prepared excel spreadsheets with significant information, they were able to quickly calculate and collaborate data. They collaborate with Devon’s consultant to ensure the job is done exactly as Devon desires.
June 7/8, 2010 – Day 11-12: Following a SCADA technician
Watched a SCADA technician perform diagnostics and maintenance on malfunctioning electrical parts. He makes sure everything in the field with wires is working. For example, we had to replace a plunger arrival sensor which had broken off and rewire it to the circuit in the well. Similarly, I observed as he replaced weak communication devices on the well and reconfigured them to exchange information with Devon’s primary server.
June 9, 2010 – Day 13: Production Logging
A Baker Hughes e-line truck performs the production logs for the well. Production logs show what is coming out of each perforation. To do this, it analyzes several conditions, including gamma ray, temperature, and density. It puts all of this information in a graph that looks very similar to an echo meter. The production log determines which formations are producing the gas and which ones are producing uneconomical amounts of water. This allows engineers to decide which formations to perforate in the future when drilling new wells and which formations to avoid.
June 10, 2010 – Day 14: Site Security Diagrams
Site security diagrams show the flow of hydrocarbons and water from the well head through the pad and into the pipeline. They are modeled with Microsoft Visio and show the various components of each well, including valves, generators, and oil tanks. Today, went to a workover rig and learned what each pipe carries and where it goes.